Time Bar: How the Right to Claim Is Lost under FIDIC

A time bar is a rule under which a party loses its claim if it did not give notice of it in time. We explain which FIDIC 2017 periods work as a time bar and how to stay clear of it.

A time bar is a contract term under which an entitlement is lost if a party does not take a formal step within a stated period. In FIDIC contracts the main such period is the 28 days for the Notice of Claim. A claim may be entirely sound on the merits and still fail because the notice was missed.

In brief: Under FIDIC 2017 the Notice of Claim is given no later than 28 days after the party became aware, or should have become aware, of the event (Sub-Clause 20.2.1). Missing the period puts the entitlement to time and money for that event at risk. The second key period is the 84 days for the fully detailed Claim (Sub-Clause 20.2.4).

Which periods work as a time bar

PeriodWhat has to be doneSub-Clause
28 daysGive the Notice of Claim20.2.1
14 daysThe Engineer may state that the notice is late20.2.2
84 daysSubmit the fully detailed Claim20.2.4
28 daysGive a NOD against an Engineer's determination or DAAB decision3.7, Cl. 21

How to stay clear of the time bar

  1. Keep an event register: what happened, when you became aware, which period is running.
  2. When in doubt, give notice: it costs nothing, and its absence costs the claim.
  3. Give the notice as a Notice, with a reference to the Sub-Clause.
  4. Do not wait for final figures: the calculation comes later, with the substantiation.
  5. Keep evidence of the date on which you became aware of the event.
Time bar: four periods not to miss
Infographic: Time bar: four periods not to miss

Frequently asked questions

Is there a time bar in the 1999 edition?

Yes. Under Sub-Clause 20.1 of the 1999 edition the Contractor also gives notice within 28 days; otherwise time is not extended and no additional payment is due.

Does the time bar apply to the Employer?

In the 2017 edition, yes: the Employer claims under the same Sub-Clause 20.2 and within the same period.

Sources and references

  • FIDIC Red Book 2017, Sub-Clauses 20.2.1 and 20.2.2
  • FIDIC Red Book 2017, Sub-Clause 20.2.4
  • FIDIC Red Book 1999, Sub-Clause 20.1

How Bridge Consult can help

Bridge Consult supports employers and contractors on FIDIC contracts — from reviewing conditions and notices to claims, DAAB proceedings and arbitration. Founder Larissa Belousova is a FIDIC Certified Consulting Engineer and an ADB Accredited Contract Management and Dispute Avoidance Specialist.

Have a question about a live contract? Contact us and we will look at your situation.