Advance Warning: Early Warning under Sub-Clause 8.4 of FIDIC
Advance Warning is the duty to warn in advance of events that may delay the Works or increase the price. It was introduced in the FIDIC 2017 edition. We explain who warns of what, and how it differs from a Notice of Claim.
Advance Warning is an early warning of a future risk to the project. The FIDIC 2017 edition introduced it in Sub-Clause 8.4: each Party and the Engineer must tell the others in advance of known or probable events that may adversely affect the work, increase the Contract Price or delay completion.
In brief: Advance Warning is the duty under Sub-Clause 8.4 of FIDIC 2017 to warn in advance of an event that may affect the work, the price or time. It is a risk-management tool, not a claim: only a Notice of Claim given within 28 days preserves the entitlement to time and money. The 1999 edition has no such duty.
What to warn about, and how
- Events that may adversely affect the work of the Contractor’s Personnel.
- Anything that may adversely affect the performance of the Works when completed.
- Anything that may increase the Contract Price.
- Anything that may delay the execution of the Works or a Section.
- The warning is given by whoever learns of the risk first: the Contractor, the Employer or the Engineer.
Advance Warning and Notice of Claim are not the same
| Advance Warning (8.4) | Notice of Claim (20.2.1) |
|---|---|
| About | A future risk |
| Purpose | To avoid or reduce the problem together |
| When | In advance, as soon as known |
| Replaces the other? | No |

Frequently asked questions
Is there an Advance Warning in the 1999 edition?
No. It is a new obligation of the 2017 edition.
Does an Advance Warning preserve the right to claim?
No. If the risk materialises, a separate Notice of Claim must be given within 28 days.
Sources and references
- FIDIC Red Book 2017, Sub-Clause 8.4
- FIDIC Red Book 2017, Sub-Clause 20.2.1
How Bridge Consult can help
Bridge Consult supports employers and contractors on FIDIC contracts — from reviewing conditions and notices to claims, DAAB proceedings and arbitration. Founder Larissa Belousova is a FIDIC Certified Consulting Engineer and an ADB Accredited Contract Management and Dispute Avoidance Specialist.
Have a question about a live contract? Contact us and we will look at your situation.