Defects Notification Period (DNP) in FIDIC Contracts

The Defects Notification Period is the period after taking over during which the Employer notifies defects and the Contractor remedies them. We explain how long it lasts, how it ends and what the Performance Certificate is.

The Defects Notification Period (DNP) is the period after taking over of the Works during which the Employer may notify defects and the Contractor must remedy them. In the FIDIC 2017 edition it is dealt with in Clause 11. In practice it is often called the defects liability period.

In brief: The DNP starts on the taking-over date. Its length is stated in the Contract Data and, if not stated, is one year. After the last DNP expires the Engineer issues the Performance Certificate within 28 days (Sub-Clause 11.9): only that document confirms that the Contractor has performed its obligations.

How the defects period works

  • It starts on the completion date stated in the Taking-Over Certificate.
  • Its length is as stated in the Contract Data; if not stated, one year.
  • The Contractor completes outstanding work and remedies the defects the Employer has notified.
  • After it ends the second half of the Retention Money is released (Sub-Clause 14.9).
  • It closes with the Performance Certificate, within 28 days after the last DNP expires (Sub-Clause 11.9).

Common mistakes

  • The Taking-Over Certificate is taken for the end of the Contractor’s obligations.
  • A defect is reported orally, with no notice and no record of the date.
  • The DNP is left blank in the Contract Data and the Parties count its end differently.
  • The FIDIC defects period is confused with warranty periods under national law: the two may run in parallel.
From taking over to the Performance Certificate
Infographic: From taking over to the Performance Certificate

Frequently asked questions

How long is the Defects Notification Period?

As long as the Contract Data states. If no period is stated, under the FIDIC 2017 General Conditions it is one year.

What is the Performance Certificate?

It is the certificate the Engineer issues after the defects period ends. It alone confirms that the Contractor has performed its obligations under the contract.

Sources and references

  • FIDIC Red Book 2017, Clause 11
  • FIDIC Red Book 2017, Sub-Clause 11.9
  • FIDIC Red Book 2017, Sub-Clause 14.9

How Bridge Consult can help

Bridge Consult supports employers and contractors on FIDIC contracts — from reviewing conditions and notices to claims, DAAB proceedings and arbitration. Founder Larissa Belousova is a FIDIC Certified Consulting Engineer and an ADB Accredited Contract Management and Dispute Avoidance Specialist.

Have a question about a live contract? Contact us and we will look at your situation.

This term in our articles

Other terms

Telegram channel

FIDIC Uzbekistan

Expert materials, case studies and event announcements on FIDIC contracts in Central Asia — before they reach the site.

Subscribe