NOD (Notice of Dissatisfaction): Meaning and Time Limits in FIDIC
A NOD is a notice of dissatisfaction with an Engineer's determination or a DAAB decision. Without it the decision becomes final. We explain when and how to give one under FIDIC 2017.
A NOD (Notice of Dissatisfaction) is a written notice that a Party is dissatisfied with an Engineer’s determination or a DAAB decision. It is a short document with great weight: if it is not given in time, the determination or decision becomes final and binding and can no longer be challenged.
In brief: A NOD is given within 28 days: after an Engineer’s determination under Sub-Clause 3.7 and after a DAAB decision under Clause 21. After a NOD against a DAAB decision the Parties have 28 days to attempt amicable settlement, then arbitration may follow. Missing the period makes the determination or decision final.
Two situations that call for a NOD
| Engineer's determination | DAAB decision |
|---|---|
| Basis | Sub-Clause 3.7 |
| Period | 28 days |
| What follows | The dispute may be referred to the DAAB |
| If the period is missed | The determination is final and binding |
How to give a NOD properly
- Identify the document as a Notice of Dissatisfaction and refer to the Sub-Clause.
- State what exactly you are dissatisfied with and, briefly, why.
- Send it to the other Party and the Engineer (or the DAAB) by a method the contract accepts for notices.
- Keep complying with the determination or decision: a NOD does not suspend it.

Common mistakes
- The NOD is a few days late and the right to dispute is lost.
- Dissatisfaction is voiced in correspondence but not given as a notice.
- A Party gives a NOD and stops complying with the decision, creating a new breach of its own.
- The NOD covers only part of the decision although the Party later wants to dispute all of it.
Frequently asked questions
Does a NOD suspend compliance with the decision?
No. An Engineer’s determination and a DAAB decision are complied with at once even if a NOD has been given. The notice only preserves the right to take the dispute further.
Can a NOD be given against part of a decision?
Yes, but the rest then becomes final and binding. State clearly which parts you dispute.
Sources and references
- FIDIC Red Book 2017, Sub-Clause 3.7
- FIDIC Red Book 2017, Clause 21
How Bridge Consult can help
Bridge Consult supports employers and contractors on FIDIC contracts — from reviewing conditions and notices to claims, DAAB proceedings and arbitration. Founder Larissa Belousova is a FIDIC Certified Consulting Engineer and an ADB Accredited Contract Management and Dispute Avoidance Specialist.
Have a question about a live contract? Contact us and we will look at your situation.
This term in our articles
- FIDIC DAB vs DAAB: what's the difference, and why it matters not to confuse the abbreviations in your contract
- International Arbitration Against Turkish Investors: What It Means for FIDIC Contracts
- New Bukhara Airport PPP: Which FIDIC Form, Key Risks and a Pre-Signing Checklist
- What Is a DAAB under FIDIC Contracts — and Why Your Project Needs One
Other terms
FIDIC Uzbekistan
Expert materials, case studies and event announcements on FIDIC contracts in Central Asia — before they reach the site.