NOD (Notice of Dissatisfaction): Meaning and Time Limits in FIDIC

A NOD is a notice of dissatisfaction with an Engineer's determination or a DAAB decision. Without it the decision becomes final. We explain when and how to give one under FIDIC 2017.

A NOD (Notice of Dissatisfaction) is a written notice that a Party is dissatisfied with an Engineer’s determination or a DAAB decision. It is a short document with great weight: if it is not given in time, the determination or decision becomes final and binding and can no longer be challenged.

In brief: A NOD is given within 28 days: after an Engineer’s determination under Sub-Clause 3.7 and after a DAAB decision under Clause 21. After a NOD against a DAAB decision the Parties have 28 days to attempt amicable settlement, then arbitration may follow. Missing the period makes the determination or decision final.

Two situations that call for a NOD

Engineer's determinationDAAB decision
BasisSub-Clause 3.7
Period28 days
What followsThe dispute may be referred to the DAAB
If the period is missedThe determination is final and binding

How to give a NOD properly

  1. Identify the document as a Notice of Dissatisfaction and refer to the Sub-Clause.
  2. State what exactly you are dissatisfied with and, briefly, why.
  3. Send it to the other Party and the Engineer (or the DAAB) by a method the contract accepts for notices.
  4. Keep complying with the determination or decision: a NOD does not suspend it.
NOD: the route of a dispute under FIDIC 2017
Infographic: NOD: the route of a dispute under FIDIC 2017

Common mistakes

  • The NOD is a few days late and the right to dispute is lost.
  • Dissatisfaction is voiced in correspondence but not given as a notice.
  • A Party gives a NOD and stops complying with the decision, creating a new breach of its own.
  • The NOD covers only part of the decision although the Party later wants to dispute all of it.

Frequently asked questions

Does a NOD suspend compliance with the decision?

No. An Engineer’s determination and a DAAB decision are complied with at once even if a NOD has been given. The notice only preserves the right to take the dispute further.

Can a NOD be given against part of a decision?

Yes, but the rest then becomes final and binding. State clearly which parts you dispute.

Sources and references

How Bridge Consult can help

Bridge Consult supports employers and contractors on FIDIC contracts — from reviewing conditions and notices to claims, DAAB proceedings and arbitration. Founder Larissa Belousova is a FIDIC Certified Consulting Engineer and an ADB Accredited Contract Management and Dispute Avoidance Specialist.

Have a question about a live contract? Contact us and we will look at your situation.