Highway through mountain terrain at dusk — infrastructure project

BRIDGE Consult Academy · Online

FIDIC contract management in practice

Not a clause-by-clause walkthrough, but a working through of the situations that turn into claims, delays and disputes on site. The 1999 and 2017 editions, side by side.

FIDIC Certified Consulting Engineer FIDIC Certified Consulting Professional Delivered by Larisa Belousova — FCCE, FCCP, member of the FIDIC Integrity Management Committee
18

modules — from contract administration to arbitration

40+

practical cases, each analysed in the same format

15 yrs

of the trainer's specialised experience with FIDIC contracts

RU + UZ

sessions in Russian, materials and subtitles in Uzbek

About the programme

What makes this programme different

The programme is deliberately not structured as a clause-by-clause walkthrough of the conditions of contract. Its purpose is to address the real, recurring problems that Employers, Engineers, Contractors and public bodies meet in practice, and to build the ability to recognise and resolve them before they turn into an extension of time claim, an additional cost claim, a Variation dispute or a formal dispute referred to the DAAB or arbitration.

The programme is based on the FIDIC Conditions of Contract 1999 and 2017, international practice on projects financed by multilateral development banks (World Bank, ADB, AIIB, EBRD), the SCL Delay and Disruption Protocol, and established construction claims practice.

A dispute almost never begins as a dispute. It begins with a notice that was not served in time.

Method

A single format for every case

Every practical issue is analysed across the same set of fields. That moves the discussion from "what the contract says" to a management decision — and makes the analysis repeatable: participants apply the same format to their own projects after the programme.

Anatomy of a case
Practical issue record the same format for all 40+ cases
01Practical issuethe specific problem
02Typical scenariowhat usually happens on site
03Time impacteffect on the programme and completion
04Cost impacteffect on project cost and cash flow
05Relevant FIDIC clausesapplicable sub-clauses of the 1999 and 2017 editions
06Common mistakesset out separately for the Employer, the Engineer and the Contractor
07Learning objectivethe competence participants acquire
08Practical examplea scenario for group work
Contents

18 modules — from contract administration to arbitration

I

Time and programme

How the contract is run from day one decides whether a party has any entitlement at all.

Gantt chart and dividers — time and programme management
01Contract administration
02Programme management
03Time management
04Extension of time
05Delay analysis
II

Money and variations

Where a project loses value — and at what point it can still be stopped.

Cost curves on glass — variations and cost control
06Variations
07Claims
08Payment
09Cost control
III

Roles and the site

Who is obliged to do what under the contract, and what evidences it in the project record.

Drawing and plumb bob — party roles and site management
10The role of the Engineer
11Employer's obligations
12Contractor's obligations
13Site management
14Records kept during the works
IV

Risk and disputes

What to do once avoidance has failed — and how not to lose on procedure.

Glass panels and gavel — risk, dispute avoidance and arbitration
15Risk allocation
16Dispute avoidance
17DAAB
18Arbitration
A worked example

Compliance with time-bar provisions for notices

One of the key issues in the first module. This is how each of the programme's forty-plus cases is set out — and how participants then work through their own situations.

Case 01.3 1999 — SC 20.1 2017 — SC 20.1–20.2

Typical situation

Site staff are aware of an event affecting time or cost, but the Engineer is not notified within the contractual period, on the assumption that an oral report or a mention at a progress meeting is enough.

Result

The entitlement to an extension of time is put at risk regardless of the merits, and the dispute shifts from the event itself to the missed time bar.

Practical takeaway

Maintain a live notice register and distinguish the "as soon as practicable" requirement from the 28-day condition precedent.

Who it is for

For those accountable for the contract, not only reading it

The programme is addressed to the public authorities and state employers of Uzbekistan delivering infrastructure projects — including the Ministry of Construction, the Ministry of Transport, JSC Uzsuvtaminot and the State Expertise under the Ministry of Construction — as well as project employers, engineers, consultants and project managers.

01

Public employers

Understand which Employer obligations create grounds for Contractor claims, and close them out before a claim is served.

02

Engineers and consultants

Make determinations under SC 3.5 / 3.7 that hold up before a DAAB and in arbitration.

03

Contractors

Avoid losing entitlement to EOT and additional cost through defective notices and missing records.

04

Project managers

See the link between the programme of works, site records and project cash flow.

Format

Live sessions online — the recording stays with the participant

The programme is delivered as a workshop with case work in groups. Sub-clause references are given in parallel for the 1999 edition (Red and Yellow Books, with the numbering broadly applicable to the Silver Book) and the 2017 edition, and are always to be checked against the Particular Conditions of the specific project — these most often modify the General Conditions.

Sessions in Russian

Live, with questions and analysis of the participants' own situations. Every session is recorded.

Materials in two languages

Slides, handouts and the FIDIC terminology glossary are prepared in Russian and Uzbek.

Uzbek subtitles for recordings

The translation is reviewed by a contracts specialist, not a general translator: in FIDIC, precision of terminology is the substance.

Tailored to the organisation

Modules and cases can be assembled around a specific project and the employer's own contract.

Trainer
Larisa Belousova
FIDIC Certified Consulting Engineer FIDIC Certified Consulting Professional CIArb — Chartered Institute of Arbitrators DRBF — Dispute Resolution Board Foundation

Larisa Konstantinovna Belousova

Infrastructure Contracts · FIDIC · EPC and EPC+F · Procurement · Claims · Dispute Avoidance · International Arbitration

Larisa Belousova is an international infrastructure contracts, procurement and construction disputes specialist with 27 years of management experience in manufacturing, construction, logistics and procurement, including more than 15 years of specialised experience in FIDIC contract management and IFI-financed infrastructure projects.

Her sector experience covers roads and highways, bridges and tunnels, transport and airport infrastructure, urban and public infrastructure, water supply and wastewater, energy and other major infrastructure projects.

She specialises in FIDIC contract administration, EPC and EPC+F contract structuring, procurement and tender documentation, variation and claims management, delay and quantum analysis, contractual and commercial risk management, dispute avoidance and construction dispute resolution.

Larisa is a FIDIC Certified Consulting Engineer (FCCE) and FIDIC Certified Consulting Professional (FCCP). She has practical experience with the FIDIC Red Book, Yellow Book, Silver Book, MDB Harmonised Editions, Subcontract Book and White Book. She is also an ADB Accredited Contract Management and Dispute Avoidance Specialist.

As Founder and Director of BRIDGE Consult LLC, she advises government authorities, employers, contractors, engineers and consulting firms on the preparation and administration of infrastructure contracts, procurement, claims, contractual and commercial risks, dispute avoidance and preparation for arbitration proceedings across Central Asia.

Professional accreditations & memberships

  • Member of the FCCE Certification Committee, FIDIC Credentialing
  • Member of the FIDIC Integrity Management Committee
  • FCCE — FIDIC Certified Consulting Engineer
  • FCCP — FIDIC Certified Consulting Professional
  • ADB Accredited Contract Management and Dispute Avoidance Specialist
  • MCIArb — Member of the Chartered Institute of Arbitrators
  • Member of the LCIA European Users’ Council
  • ICAA Next Generation Member
  • Arbitrator, International Commercial Arbitration Court under the Chamber of Commerce and Industry of the Republic of Uzbekistan (ICAC Uzbekistan)
  • Member of the Austrian Arbitration Association
  • DRBF Emerging Markets Licensed Professional and Dispute Board Practitioner
  • Independent Mediator registered with the Ministry of Justice of the Republic of Uzbekistan
  • Full Member of the Kazakhstan National Association of Professional Engineers and Consultants (KNAPEK)
  • Board Member of the Uzbekistan Road Association
  • Member of the Project Management Institute (PMI)
  • PCQI — Practitioner of the Chartered Quality Institute (CQI), UK
  • ICAgile Certified Professional (ICP)

Download CV (PDF)

Apply

We will send the programme and the next intake dates

Tell us who the training is for and which contractual situations you would like to work through. We answer every enquiry personally.

  • The full 18-module programme as a PDF
  • Dates and schedule of the next intake
  • Terms for a group from a single organisation
  • Invoice and contract for bank transfer payment

Or write to us directly: info@bridgeconsult.uz