RU EN UZ
All news
FIDICClaimsEOT

EOT: How a Contractor Can Lawfully Extend Time and Avoid Delay Damages

Bridge Consult
EOT: How a Contractor Can Lawfully Extend Time and Avoid Delay Damages

An Extension of Time is the contractor's main shield when delays are not its fault. We break down which events give a right to EOT under FIDIC, why a claim expires after 28 days, and which records decide the outcome of a dispute.

Missing the Time for Completion is the contractor’s most expensive risk: behind it stand delay damages, deductions under guarantees and a damaged reputation. Yet far from every delay is the builder’s fault. For exactly these situations the FIDIC forms provide the EOT (Extension of Time) — an extension of the Time for Completion that relieves the contractor of liability for delay damages.

Which events give a right to an EOT

Sub-Clause 8.5 of the FIDIC 2017 conditions and the provisions linked to it list the typical grounds:

  • Variations — the employer has expanded or changed the scope of works;
  • Employer-caused delays: late access to the site, late drawings or permits;
  • Unforeseeable physical conditions (Sub-Clause 4.12) — for example, ground conditions absent from the site data;
  • Exceptional Events (the former force majeure);
  • acts of authorities, delayed inspections and tests not attributable to the contractor.

Important: the right to an EOT does not arise automatically. It must be claimed and proven.

The 28-day rule: why claims expire

Under Sub-Clause 20.2.1 of FIDIC 2017 the contractor must give a Notice of Claim within 28 days of when it became aware, or should have become aware, of the event. Miss the deadline — and the right to time and money is lost, however well-founded the claim may be on the merits. This is the most frequent and the most expensive mistake contractors make on FIDIC projects.

The procedure then requires a fully detailed claim within 84 days: a description of the event, the contractual basis, and a calculation of the delay and additional cost.

What decides the outcome: records and the programme

An EOT is won with documents, not emotions:

  1. An up-to-date works programme (Sub-Clause 8.3) — without an approved programme it is impossible to show how the event affected the critical path.
  2. Contemporary records: site diaries, correspondence, photo records, weather data, timesheets.
  3. Causation: delay analysis methods under the SCL Protocol (Time Impact Analysis, Windows Analysis) show which delay actually moved the completion date — critical where there is concurrent delay, when both parties are at fault.

Frequent mistakes

  • Notifying “once the scale of the problem is clear” — instead of 28 days from the event.
  • A claim with no reference to a specific clause of the contract.
  • A calculation of “we were delayed 60 days, give us 60 days” without critical-path analysis.
  • No records: a year after the event the picture is almost impossible to reconstruct.

How Bridge Consult can help

Bridge Consult supports claims management on FIDIC projects: from setting up notice and record-keeping systems to preparing EOT claims and defending the position before the Engineer, the DAAB and in arbitration. Our expert performs Forensic Delay Analysis to the international SCL Protocol methodologies — including retrospective analysis of delays that have already occurred.

Received a delay damages notice, or feel the project slipping? Contact us — the earlier claims work starts, the higher the chances of an EOT.

Read next

Telegram channel

FIDIC Uzbekistan

Expert materials, case studies and event announcements on FIDIC contracts in Central Asia — before they reach the site.

Subscribe